Stephen J. Gowdy wrote:

Can't you get get that person to work 16 hours that day? FWIW I think the
non-free version of project management would do the same as planner does.

As far as I recall, when I last used a commercial project planner it would only allow double booking of resources if specifically allowed. The default was to string them in time from end to end in order that they were found.

The other really useful thing that I found was that if you had not marked a task as complete and it was due to complete yesterday, it would move it forwards and automatically adjust project slippage. You could therefore have a realistic view of where the project was to time-lines without having to readjust for every little date.

Kind regards
Xander