Re: [Planner] Tasks with fixed deadlines
- From: Richard Hult <richard imendio com>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Tasks with fixed deadlines
- Date: Wed, 09 Mar 2005 00:22:11 +0100
Struan Bartlett wrote:
Hi -
Hi,
So, for these deadlined project components I need the end-date fixed and
the start-date calculated according to the duration of the work that
preceeds it, which is something I can't see how to do. Is the
functionality available or in planning?
It's not currently available but it's an important feature that would be
good to have. There are no immediate plans to add it, but it someone
wants to help out that would be great.
/Richard
--