[Planner] Tasks with fixed deadlines
- From: Struan Bartlett <struan praguespringpeople org>
- To: Planner Project Manager <planner lists imendio com>
- Subject: [Planner] Tasks with fixed deadlines
- Date: Mon, 07 Mar 2005 16:29:04 +0100
Hi -
In inputting my projects into Planner I've run up against a barrier:
many of my tasks have fixed deadlines because of externally-agreed
constraints. They simply have to happen by a certain date and everything
that needs to come before or after needs to be calculated around that date.
For example, I have a quarterly report due on the 11th of May, Aug, Nov
and Feb. It takes about 5 working days to prepare, but it must be
delivered by that date. I have a bi-annual meeting on the 25th of May
and Nov each year. The meeting lasts a day, but there are various tasks
that it depends on being completed in advance that take up a couple of
days between them. (Incidentally, to plan the rest of my year, I need to
slot other projects in around these fixed points).
So, for these deadlined project components I need the end-date fixed and
the start-date calculated according to the duration of the work that
preceeds it, which is something I can't see how to do. Is the
functionality available or in planning?
Best regards,
Struan Bartlett
[