On Fri, Feb 18, 2011 at 11:27 AM, fox <fox orbitalfox com> wrote:
> It would be nice if there was an indication in the month view that the
> resource is unavailable (e.g. greyed out).

Greyed out days are non-working days on the default calendar. These
are supposed to be the common ones.

If a resource is assigned another calendar, it may have specific
non-working days. Those should NOT appear on the month view as they
are specific to the resources using this calendar, or you may end up
having working days greyed out.

-- 