Re: Planner-list Irregular vacation dates



On 17/02/11 15:49, Alexandre Franke wrote:
> On Thu, Feb 17, 2011 at 3:09 PM, fox <fox orbitalfox com> wrote:
>> Hi,
> 
> Hi.
> 
>> Is there a way to have irregular vacation dates for resources? If yes,
>> do they remove the resource from a tasks completion time calculation?
> 
> Yes. In resource view, edit rescource, go to calendar tab, edit
> calendars and simply set vacation days as non-working days for the
> calendar you'll assign to this resource.
> 
> P.S.: you should subscribe to the mailing list if you want to get
> answers for your questions. I had to manually accept your mail as
> posts from non-subscribed people are moderated.
> 

Thank you this worked!

It would be nice if there was an indication in the month view that the
resource is unavailable (e.g. greyed out).

But it does recalculation completion time.


[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]