Re: [Planner] Are fixed duration tasks really fixed?




It seems as if 1day = 8h in any case. How is this motivated? For my
chemical process time runs every minute every day (the same goes for the
pregnant woman as we agreed ;-) ). How do I specify this?

Regards,
Björn



I've noticed few places where there is the number 8 x 60 x 60
hard coded. I'd never looked deeper but raised,
http://bugzilla.gnome.org/show_bug.cgi?id=134383

planner-task-tree.c
planner-resource-view.c
planner-task-input-dialog.c
planner-project-properties.c
planner-task-dialog.c
mrp-project.c
mrp-old-xml.c
mrp-task.c

is what I found on grep.