Re: [Planner] Making tasks start later



tor 2004-02-26 klockan 14.26 skrev Nicholas Piper:
> I have two major tasks with children, 'Site D migration' and 'Site A
> migration'. My project starts say, 1st May 2004.
> 
> Site D migration has a final task 'Train Staff', which can't happen
> until Site A has 'Returned to corporate LAN'. 
> 
> That means site D items start, then there is a long wait until 'Train
> Staff', due to site A generally having more complex items.
> 
> How can I delay the start of all the site D items so there isn't such
> a wait?
> 
> I don't mind tweaking by hand. What's the best way to do it?

I'm not sure I follow your exact example but there is generally two ways
to delay tasks:

1. Add relations between tasks (click on a task and drag to another)

2. Set a constraint, which is done in the task view, click the start
date cell and choose "Start no earlier than"m or "Must start on".

Hope it helps
/Richard

-- 