Re: [Planner] Making tasks start later
- From: Nicholas Piper <nick-planner nickpiper co uk>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Making tasks start later
- Date: Thu, 26 Feb 2004 22:38:26 +0000
Richard,
On Thu, 26 Feb 2004, Richard Hult wrote:
> I'm not sure I follow your exact example but there is generally two ways
> to delay tasks:
> 1. Add relations between tasks (click on a task and drag to another)
> 2. Set a constraint, which is done in the task view, click the start
> date cell and choose "Start no earlier than"m or "Must start on".
Ah, I didn't notice this UI before. That lets me do what I need to do,
thank you.
It would be nice to be able to set "Start no earlier than" on a group
of tasks, but I can do each by hand for now :-)
Nick
--
Part 4 MEng Cybernetics; Reading, UK http://www.nickpiper.co.uk/
GPG Encrypted mail welcome! 1024D/3ED8B27F
Choose life. Be Vegan :-) Please reduce needless cruelty + suffering !
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]