- From: Nicholas Piper <nick-planner nickpiper co uk>
- To: planner lists imendio com
- Subject: [Planner] Making tasks start later
- Date: Thu, 26 Feb 2004 13:26:13 +0000
I have two major tasks with children, 'Site D migration' and 'Site A
migration'. My project starts say, 1st May 2004.
Site D migration has a final task 'Train Staff', which can't happen
until Site A has 'Returned to corporate LAN'.
That means site D items start, then there is a long wait until 'Train
Staff', due to site A generally having more complex items.
How can I delay the start of all the site D items so there isn't such
a wait?
I don't mind tweaking by hand. What's the best way to do it?
Nick
--
Part 4 MEng Cybernetics; Reading, UK http://www.nickpiper.co.uk/
GPG Encrypted mail welcome! 1024D/3ED8B27F
Choose life. Be Vegan :-) Please reduce needless cruelty + suffering !
[