Re: [Planner Dev] lag & more



On Tue, 2004-08-31 at 09:59, Richard Hult wrote:
> On tis, 2004-08-31 at 09:38 -0400, Kurt Maute wrote:
> > Personally, I think it should be derived from the default calendar ('Working' day type).  Likewise with the default work week.  Some folks might use a 6 or 4 day default work week, so that should be taken into account also.
> > IMO, if I changed my default calendar to be 9 hour days, then it might be confusing to have to go change a setting as well.
> 
> That might be a good way. So we could always use the project calendar
> (which is used as default if no other is specified for resources), even
> if resources might use another calendar, right?

Right.  The default calendar would always be used when entering work in
days or weeks, but then duration would be calculated either against the
resource specific calendar, or the default if no resource has been
assigned yet.

-- 
Kurt Maute <kurt maute us>