Re: Planner-list make Schedule "On fixed date" (Today) the default / automatically compute "% Complete"
- From: Alexandre Franke <alexandre franke gmail com>
- To: Steve Kieffer <kieffer steve gmail com>
- Cc: planner-list gnome org
- Subject: Re: Planner-list make Schedule "On fixed date" (Today) the default / automatically compute "% Complete"
- Date: Thu, 21 Jul 2011 11:40:23 +0200
On Thu, Jul 21, 2011 at 12:40 AM, Steve Kieffer <kieffer steve gmail com> wrote:
> Hi,
Hi,
> 1. I'd like to make it so that when I insert a new task the default Schedule
> is "On fixed date" (and have the default date be "Today") rather than "As
> soon as possible". Is there a way to do this?
We don't support this and this doesn't sound like something we are
likely to implement.
> 2. Is there a way to make the entries in the "% Complete" column automatic,
> for tasks that have subtasks? This should take duration of subtasks into
> account.
There's a feature request for that at
https://bugzilla.gnome.org/show_bug.cgi?id=561000
Add yourself to CC and you'll be notified when something new happens.
--
Alexandre Franke
[