Re: Planner-list there is no way to move task in time off ?



On 2010-02-19 08:52:46 +0100 (Fri, Feb), Gabriel Rota wrote:
> Il giorno ven, 19/02/2010 alle 03.44 +0100, Alexandre Franke ha scritto:
> > 2010/2/18 Gabriel Rota <gabriel rota gmail com>:
> > > my coworker have necessity to add a task in time off like for a day
> > > because activity cannot execute on used server.
> > 
> > I don't really understand what you're trying to do, can you please
> > explain it with other words?
> 
> thanks for answer
> 
> I try to explain and when I arrive at office I ask at my coworker give
> me the gantt generated as image and post here as link.
> 
> All task in planner can be planned by hour in work time default 8.00 -
> 17.00.
> For a day my coworker have planned a server down in time off like 18.30
> to 19.30.
> Other day have a normal time.

I suppose you need to use menu: "Project->Edit Day Types" and add a new
day type. The hard part will be to choose a name for this type ;-).
Let's call it 'Maintenance' or 'Working and Maintenance' or 'Working
late'.

Then go to "Project->Manage Calendars", select the calendar in the left
column (if you have created more calendars).
Click the button [Working time...], select the just-created-day-type,
type the hours (8:00 - 17:00 / 18:30 - 19:30, for example) and click
[Apply], then [Close].

Select the day you want to change (February 19, for example) and near
the bottom you will see an option 'Set day type to:'.
Choose the just-created-day-type and click [Apply].

I hope this helps. :)