Re: Planner-list there is no way to move task in time off ?



2010/2/19 Gabriel Rota <gabriel rota gmail com>:
> All task in planner can be planned by hour in work time default 8.00 -
> 17.00.
> For a day my coworker have planned a server down in time off like 18.30
> to 19.30.
> Other day have a normal time.

I think I see what you mean now : you would like to have a task happen
during non-working days.

That can be easily achieved. Here's how:
* create a new resource (for instance "Computer") that will work on your task
* edit calendar for this resource, maybe create a new calendar
* set the days when the work should be done as working days in this calendar
* assign tasks to the resource

Result: the tasks will be worked on even on weekends.

-- 
Alexandre Franke