I am not using Planner but keep an interest in it.  My work around this would 
be to include the fixed price contract as materials and if you need to track 
progress, place the contract in the labour dept. and award it zero hourly 
rate.

Hope this is of help
Max



> On Wed, Aug 26, 2009 at 6:36 PM, Dominic Burns<dburns lovetek co uk> wrote:
> > Hi all,
>
> Hi,
>
> > I have hit a small snag when assigning costs to resources - it seems that
> > the cost for work is based on an hourly rate but often tradesmen will do
> > work on a 'price' basis - does anyone know if there's a workaround for
> > this or am I missing something obvious?
>
> I don't think we currently provide a way to do this.
>
> > Also, is there a list archive somewhere that I can dig through?
>
> http://mail.gnome.org/archives/planner-list/