Re: [Planner] Tasks assigned to same resource scheduled concurrently?
- From: Roberto Leibman <roberto leibman net>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Tasks assigned to same resource scheduled concurrently?
- Date: Thu, 03 Mar 2005 11:01:09 -0800
Tom Miller wrote:
Roberto,
Good point(s). Um, are there any nice tools which do
Critical Chain stuff?
The only one I'm aware of (and it's been a while since I've seen/used
it) is an add-on to MS Project called ProChain, developed by (IIRC) Rob
Newbold, a very knowleadgable person on the theory of the whole thing,
but it was very hackish. I've always dreamed of creating one, but it
would require time/effort. As I said before, maybe next time I'm doing
heavy PMing (currently I only need to PM myself, so I'm the only
resource available).
Tom
On Thu, 2005-03-03 at 09:35, Roberto Leibman wrote:
<rant>
It's funny that what's perfectly obvious to someone new to project
management is ignored by most experts.
I have to agree with Josep that any tool that does project management
has to make resource constraints a first-order problem, and not an
afterthought. I've yet to see any widely used tool that does this;
Primavera, MS Project, etc don't do it, they all require you to go
through hoops to do resource leveling and most of the time you end up
having to create artificial temporal dependencies such as the suggestion
given to Josep. These dependencies are at best a workaround, but in
practice they can be detrimental to the project because they obscure the
possibility of doing tasks in parallel by the "simple" addition of
resources to a task, in practice, as the project progresses you figure
out that the link is artificial and often end up doing the task in
parallel anyway, thereby throwing your hands in the air and saying:
"screw this project plan", or even worse, spending another couple of
hours redoing the whole thing (and then an hour's meeting explaining the
"new and improved" project plan to the team.
Which is why there exist better methodologies than Critical Path
analysis (yeah, I know, I repeat myself) such as Critical Chain
management, that take into account resource constraints from the beginning.
</rant>
Josep Monés i Teixidor wrote:
El dj 03 de 03 del 2005 a les 13:56 +0100, en/na Max Lists va escriure:
Hi,
You have to "link" the 2 sub task to tell task2 goes after task1.
File attached.
Ah Ok! I knew I could do it this way but I expected the software to do
that automatically, because tasks aren't conceptually sequential, it's
just a resource problem. If I assign, for instance, task2 to another
resource, I have also to remember unlinking it (and possibly unlinking
and relinking many tasks which depended on task2).
Thanks very much.
Josep
_______________________________________________
Planner mailing list
Planner lists imendio com
http://lists.imendio.com/mailman/listinfo/planner
_______________________________________________
Planner mailing list
Planner lists imendio com
http://lists.imendio.com/mailman/listinfo/planner
_______________________________________________
Planner mailing list
Planner lists imendio com
http://lists.imendio.com/mailman/listinfo/planner
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]