Re: [Planner] Tasks assigned to same resource scheduled concurrently?
- From: Tom Miller <trm xpedion com>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Tasks assigned to same resource scheduled concurrently?
- Date: Thu, 03 Mar 2005 11:23:26 -0800
Roberto,
Thanks... I wonder if Newbold could be contacted to contribute
to this discussion somehow.
Tom
On Thu, 2005-03-03 at 11:01, Roberto Leibman wrote:
> Tom Miller wrote:
>
> >Roberto,
> >
> > Good point(s). Um, are there any nice tools which do
> > Critical Chain stuff?
> >
> >
> >
> The only one I'm aware of (and it's been a while since I've seen/used
> it) is an add-on to MS Project called ProChain, developed by (IIRC) Rob
> Newbold, a very knowleadgable person on the theory of the whole thing,
> but it was very hackish. I've always dreamed of creating one, but it
> would require time/effort. As I said before, maybe next time I'm doing
> heavy PMing (currently I only need to PM myself, so I'm the only
> resource available).
>
> > Tom
> >
> >On Thu, 2005-03-03 at 09:35, Roberto Leibman wrote:
> >
> >
> >><rant>
> >>It's funny that what's perfectly obvious to someone new to project
> >>management is ignored by most experts.
> >>
> >>I have to agree with Josep that any tool that does project management
> >>has to make resource constraints a first-order problem, and not an
> >>afterthought. I've yet to see any widely used tool that does this;
> >>Primavera, MS Project, etc don't do it, they all require you to go
> >>through hoops to do resource leveling and most of the time you end up
> >>having to create artificial temporal dependencies such as the suggestion
> >>given to Josep. These dependencies are at best a workaround, but in
> >>practice they can be detrimental to the project because they obscure the
> >>possibility of doing tasks in parallel by the "simple" addition of
> >>resources to a task, in practice, as the project progresses you figure
> >>out that the link is artificial and often end up doing the task in
> >>parallel anyway, thereby throwing your hands in the air and saying:
> >>"screw this project plan", or even worse, spending another couple of
> >>hours redoing the whole thing (and then an hour's meeting explaining the
> >>"new and improved" project plan to the team.
> >>
> >>Which is why there exist better methodologies than Critical Path
> >>analysis (yeah, I know, I repeat myself) such as Critical Chain
> >>management, that take into account resource constraints from the beginning.
> >></rant>
> >>
> >>Josep Monés i Teixidor wrote:
> >>
> >>
> >>
> >>>El dj 03 de 03 del 2005 a les 13:56 +0100, en/na Max Lists va escriure:
> >>>
> >>>
> >>>
> >>>
> >>>>Hi,
> >>>>
> >>>>You have to "link" the 2 sub task to tell task2 goes after task1.
> >>>>
> >>>>File attached.
> >>>>
> >>>>
> >>>>
> >>>>
> >>>>
> >>>Ah Ok! I knew I could do it this way but I expected the software to do
> >>>that automatically, because tasks aren't conceptually sequential, it's
> >>>just a resource problem. If I assign, for instance, task2 to another
> >>>resource, I have also to remember unlinking it (and possibly unlinking
> >>>and relinking many tasks which depended on task2).
> >>>
> >>>Thanks very much.
> >>>
> >>>Josep
> >>>
> >>>
> >>>
> >>>_______________________________________________
> >>>Planner mailing list
> >>>Planner lists imendio com
> >>>http://lists.imendio.com/mailman/listinfo/planner
> >>>
> >>>
> >>>
> >>>
> >>_______________________________________________
> >>Planner mailing list
> >>Planner lists imendio com
> >>http://lists.imendio.com/mailman/listinfo/planner
> >>
> >>
> >
> >_______________________________________________
> >Planner mailing list
> >Planner lists imendio com
> >http://lists.imendio.com/mailman/listinfo/planner
> >
> >
>
> _______________________________________________
> Planner mailing list
> Planner lists imendio com
> http://lists.imendio.com/mailman/listinfo/planner
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]