[Planner] Constraint on resource
- From: Darrell Esau <Darrell Esau Sun COM>
- To: planner lists imendio com
- Subject: [Planner] Constraint on resource
- Date: Mon, 14 Jun 2004 13:57:20 -0700
Hello,
I'm having trouble making Planner do what I want -- it is very possible it's
just a misunderstanding on my part.
This is what I'm trying to make happen:
I create a new project, add 1 resource (Joe/Work).
I then create 1 task which has a duration of 1 day and assign Joe 100%.
I then create another task which has a duration of 1 day and assign Joe 100%.
I would expect that Joe can only put out 1 day of work in 1 day, which would
mean that it would take 2 days to complete these two tasks (given the current
resource allocation).
However, Planner shows that Joe can do these in parallel and it will only take
1 day total.
I understand that I can link the two with a predecessor link, however is there
any way to get Planner to count resource allocation into the completion
dates?
Thanks,
-darrell
[