[Planner] Question.
- From: Paco Ros <paco bergantells net>
- To: planner lists imendio com
- Subject: [Planner] Question.
- Date: Sun, 26 Dec 2004 14:05:19 +0100
Hello!
I've just begun to use Planner as project management tool.
In MS Project exists a tasks property called something like "not effort
conditioned" (I'm spanish, this is exactly "No condicionada por el esfuerzo")
This property means that a task can begin one day, end another day and have a
different number of resourve usage hours.
i.e. Buying a computer. It could start January 1st, end January 31st and have
only 10 hours of dedication. This happen because you begin reading catalogs
on Jan 1st and you make a order. The task continues until the computer is
delivered to destination on Jan 31st.
Is important to make the task end on Jan 31st because Software installation
cannot begin before the computer delivery.
I don't know if this explanation can help you to answer my question. :-)
Can I do the same thing with planner? I'm using planner 0.12 from Debian Sid.
Thanks in advance for your help.
Kind regards.
--
Paco.
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]