On Sun, 2004-12-26 at 08:05, Paco Ros wrote:
> I've just begun to use Planner as project management tool.
> In MS Project exists a tasks property called something like "not effort 
> conditioned" (I'm spanish, this is exactly "No condicionada por el esfuerzo") 
> 
> This property means that a task can begin one day, end another day and have a 
> different number of resourve usage hours.
> 
> i.e. Buying a computer. It could start January 1st, end January 31st and have 
> only 10 hours of dedication. This happen because you begin reading catalogs 
> on Jan 1st and you make a order. The task continues until the computer is 
> delivered to destination on Jan 31st.

Sounds to me like you could just set the task as 'fixed duration' in the
'edit task' dialog and set the duration so that it ends on Jan 31.

Hope this helps.
-- 
Kurt Maute <kurt maute us>