Gordon McFadden wrote:
Hi There.
Hi,
Let me repeat what I just said on IRC, for the rest of the list: There
is currently no way except linking tasks to avoid overallocation.
Originally this was by choice, but we have been discussion how to add
this recently. If someone is interested in helping out with this please
let me know.
Regards,
Richard
--