[Planner] Hi all and first question
- From: Daniel Payno <dpayno gmail com>
- To: planner lists imendio com
- Subject: [Planner] Hi all and first question
- Date: Thu, 16 Dec 2004 12:05:37 +0100
Hi,
I'm new to using project management sw. I'm very keen on being able to
use planner, but i've encountered a problem.
It seems that i've been unable to customize properly my plan calendar,
for i need to compute every single hour of every single day of the
week (mainly, including Saturday and Sunday).
I've been able to define the working hours correctly to accomplish
this (00:01-23:59 basically), but I can't seem to find a place where i
could define the 'working days' as not only monday-friday, but
sunday-saturday.
Could I redefine this easily in the sources? if i could build me a
customized planner from the sources accomplishing this, that would do
it :)
Any suggestion will be gladly read.
--
Daniel Payno
http://gul.uc3m.es/~payno
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]