Re: [Planner] Hi all and first question
- From: Kurt Maute <kurt maute us>
- To: Daniel Payno <dpayno gmail com>, Planner Project Manager <planner lists imendio com>
- Cc:
- Subject: Re: [Planner] Hi all and first question
- Date: Thu, 16 Dec 2004 09:56:44 -0500
On Thu, 2004-12-16 at 06:05, Daniel Payno wrote:
> Hi,
hi
> I'm new to using project management sw. I'm very keen on being able to
> use planner, but i've encountered a problem.
>
> It seems that i've been unable to customize properly my plan calendar,
> for i need to compute every single hour of every single day of the
> week (mainly, including Saturday and Sunday).
You should find this in the 'Default Week' button in the Calendar
Editor. You can set Saturday and Sunday to 'working' days and click
'apply' for it to take effect.
--
Kurt Maute <kurt maute us>
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]