Nick Urbanik wrote:
Dear Folks,

Thank you for a wonderful program.

I would like some resources that are materials to have a fixed cost,
whereas it seems that in the resources dialog, the only way to set the
cost is at a rate per hour.  Can planner support a fixed cost
resource, where the cost does not vary with the time taken to use it?


Not (yet). What you are after is a per-use or 1-off cost of use.
I had raised a bugzilla to track this back in April. Haven't had any
time to work on that yet,

http://bugzilla.gnome.org/show_bug.cgi?id=138936

Hope to restart again in the new year though can't promise anything
until I've moved countries.

Sorry if this is a silly question, as project management software is
fairly new to me.

planner-0.12.1-1 on FC3.


------------------------------------------------------------------------

_______________________________________________
Planner mailing list
Planner lists imendio com
http://lists.imendio.com/mailman/listinfo/planner



[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]