2012/1/20 Jérôme VÉRITÉ <jverite doyoudreamup com>:
> Hi,
Bonjour,
> I try to export a project to the HTML view with a specified start date in
> the project properties but the export start date is today instead of the
> specified date.
>
> Do you know how I can obtain a correct HTML export ?
>
> I'm using version 0.14.5.
I just tried with Planner 0.14.4, changing project start date to 10
days ago. With some test tasks, I get:
Start: January 10, 2012
Finish: January 24, 2012
Report Date: January 20, 2012
The dates are correct. Can you tell us more precisely what you get?
--
Alexandre Franke
[