> What is the definition of the 'units' value within the 'resources'
> dialogue window when editing a task?
It's a percentage. If you have two resources allocated to a 2-day task
at 100%, it means both people will be working on it full-time and the
task will be done in one day. If you have one resource allocated to a
5-day task at 50%, the person will work on it half-time and the task
will be done in ten days.
--
Alexandre Franke
[