Re: Planner-list Project resource only on specific days



On 10/25/2011 06:15 AM, Andre Rothe wrote:
> Hi,
>
> I try to define my current project with Planner.
> The project has different tasks, which have specific
> lengths. But the resource (me) can only work on some
> days of the week (Thuesday, Thursday, Friday) on the
> project. What I need is a plan, whether or not I'm out
> of the plan. The first task needs four days, but if I
> start on 24th of October it must not be done on 27. 
> of October (because I work on it on 25., 27., 28.
> and 31. of October only). So the task ends in time 
> on 31. of October.
>
> How can I configure that without manually re-calculated
> task times?
>
> Thanks a lot
> Andre
> _______________________________________________
> planner-list mailing list
> planner-list gnome org
> http://mail.gnome.org/mailman/listinfo/planner-list
>
Open the project, then select "Project" from the toolbar and then
"Manage Calendars". Either create a new calendar for yourself or change
the default workdays/hours to suit your needs.

-- 
"Reasonable people adapt themselves to the world. Unreasonable
people attempt to adapt the world to themselves. All progress,
therefore, depends on unreasonable people."
—George Bernard Shaw


[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]