Re: Planner-list Project resource only on specific days

On 10/25/2011 06:15 AM, Andre Rothe wrote:
> Hi,
> I try to define my current project with Planner.
> The project has different tasks, which have specific
> lengths. But the resource (me) can only work on some
> days of the week (Thuesday, Thursday, Friday) on the
> project. What I need is a plan, whether or not I'm out
> of the plan. The first task needs four days, but if I
> start on 24th of October it must not be done on 27. 
> of October (because I work on it on 25., 27., 28.
> and 31. of October only). So the task ends in time 
> on 31. of October.
> How can I configure that without manually re-calculated
> task times?
> Thanks a lot
> Andre
> _______________________________________________
> planner-list mailing list
> planner-list gnome org
Open the project, then select "Project" from the toolbar and then
"Manage Calendars". Either create a new calendar for yourself or change
the default workdays/hours to suit your needs.

"Reasonable people adapt themselves to the world. Unreasonable
people attempt to adapt the world to themselves. All progress,
therefore, depends on unreasonable people."
—George Bernard Shaw

[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]