Re: Planner-list Project resource only on specific days



On Tue, Oct 25, 2011 at 1:15 PM, Andre Rothe
<arothe imise uni-leipzig de> wrote:
> Hi,

Hi,

You need to be subscribed to the list to post and get answers.

> How can I configure that without manually re-calculated
> task times?

"Project → Manage calendars" to create a X calendar that suits your
needs then add yourself as a resource and set your calendar to X.

-- 
Alexandre Franke