ideally, an automated system for resource allocation would divide your twenty one-day tasks among your five resources and give some kind of wide. blurry cloud and a result of four days. Gantt charts don't support that ambiguity AFAIK, so you have to roll dice or alphebetize or anything -- and assign strings of predecessors, like you're talking about but reluctant to do. Alphebetizing them works well to communicate that they're grouped arbitrarily, unless someone misunderstands and thinks you've conveniently named them alphabetically. 

I don't accept advance appreciation btw, so you may appreciate now.

On Wed, Jul 27, 2011 at 10:50 AM, Jonathan Campbell <jcampbell remindermedia com> wrote:
Hello,

It's quite possible that I don't know enough about gantt charts and that's what has led to my dilemma but here goes.

I'm currently trying to visualize how long our next project will take. I've broken the project down into about twenty tasks that I've entered in to Planner. For the most part, these tasks don't depend on each other; they could be done in any order. The only catch is that they can't be done at the same time (we have a small staff working on this project and they'll basically be taking a task, doing it and then taking another task).

Here's an example to maybe make this more clear:
Task 1 for Resource A - 4d
Task 2 for Resource A - 1d

In this case, I'd want planner to represent that these two tasks would take 5 days total. I can't figure out a way to achieve this without saying that task one is a predecessor for task 2 or vice versa.

Any insight into this is appreciated in advance.

Thanks,

Jonathan Campbell



_______________________________________________
planner-list mailing list
planner-list gnome org
http://mail.gnome.org/mailman/listinfo/planner-list




--
"I sent you three boats, and then a helicopter! What were you expecting?"


[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]