I need a task to start Saturday and end Monday with Sunday not
being counted.
I am using Planner 0.14.3 on Fedora 14. I am having a problem
with setting the working days. Some days I work Sat but mostly
on weekdays. When I try to adjust a task so it starts on a
Saturday, it automatically moves it to the following Monday.
When I change the working dates in the calendar, it allows me to
move it to a Friday that goes right through till Monday. Is
there a way to set it up so it only does Sat through to Monday
without using Friday to Monday?
Thank you!
Randall
_______________________________________________
planner-list mailing list
planner-list gnome org
http://mail.gnome.org/mailman/listinfo/planner-list
You must click on the "Project" tab, then on "Manage Calendar" and
then click "Default Week" tab change "Saturday" from non-working to
working. Save your changes before exiting.