- From: Randall Wright <ran wright gmail com>
- To: planner-list gnome org
- Subject: Planner-list Dates / Working days
- Date: Wed, 2 Feb 2011 12:36:27 -0800
I need a task to start Saturday and end Monday with Sunday not being counted.�
I am using Planner 0.14.3 on Fedora 14. I am having a problem with setting the working days. Some days I work Sat but mostly on weekdays. When I try to adjust a task so it starts on a Saturday, it�automatically�moves it to the following Monday. When I change the working dates in the calendar, it allows me to move it to a Friday that goes right through till Monday. Is there a way to set it up so it only does Sat through to Monday without using Friday to Monday?
Thank you!
Randall