On Thu, Sep 16, 2010 at 10:55 AM, Nikolaos Konstantinou
<nkons1 gmail com> wrote:
> Dear all,
Hi,
> I would like it to be relative to the project start (M1, M2, ...).
We don't support that for the moment. Actually, that's the first time
I hear about this feature.
> The absence of this feature is really a showstopper for me and to be honest,
> only in m$ project I have seen this feature that is so important for my
> work.
I'm sorry to hear that.
> Are there plans to support such a configuration in the foreseeable future?
As I said above, it's the first time I hear about this feature. The
idea seems nice. I filed a feature request.
https://bugzilla.gnome.org/show_bug.cgi?id=629846
However, we don't plan on implementing it in the near future.
--