Thanks Alexander, but let me give an example about my sugestion. Let's suppose a proyect with a number of tasks that sum 18 hours/week of work during 6 months, but, in this proyect I can't to hire personal payed by hours, and I have to hire him part time or full time, (20 hours/week or 40 hours/week of availability). In that case, I'll have to hire the personal part time, and pay the equivalence of 20 hours/week using only 18 hours/week. If I use the value of hour, the real one, the costs of the proyect will be unreal, but if I adjust that cost only for adjust the budget, I won't see the availability of time of the people, unused time. (In this case 2 hours/week). I know that in this example, to identify the overpayed is easy, but in big proyects I could to hire unnecesary extra work. If Planner, let's me choose, the time partition and the pay (500 USD 20hours/week and not only 50 USD/hour), I could to resolve the problem of availability an cost. I hope the question will be clear for everybody. regards, Leonardo Perez > From: planner-list-request gnome org > Subject: Planner-list Digest, Vol 43, Issue 3 > To: planner-list gnome org > Date: Tue, 9 Mar 2010 12:00:12 +0000 > > Send Planner-list mailing list submissions to > planner-list gnome org > > To subscribe or unsubscribe via the World Wide Web, visit > http://mail.gnome.org/mailman/listinfo/planner-list > or, via email, send a message with subject or body 'help' to > planner-list-request gnome org > > You can reach the person managing the list at > planner-list-owner gnome org > > When replying, please edit your Subject line so it is more specific > than "Re: Contents of Planner-list digest..." > > > Today's Topics: > > 1. Re: New user and first feedback. (Alexandre Franke) > > > ---------------------------------------------------------------------- > > Message: 1 > Date: Mon, 8 Mar 2010 14:55:20 +0100 > From: Alexandre Franke <alexandre franke gmail com> > To: planner-list gnome org > Subject: Re: Planner-list New user and first feedback. > Message-ID: > <cf01fe061003080555l60231bcei11f1477aebdd104 mail gmail com> > Content-Type: text/plain; charset=UTF-8 > > On Sun, Mar 7, 2010 at 10:47 PM, Leonardo Perez <lperezal hotmail com> wrote: > > Hello. > > Hi, > > > I'm just using planner for Linux. I'm very glad to find this programme, > > using Planner, I'll never go back to Windows and MS Proyect. > > I'm Engieneer and I use MS Proyect constantly. I found that in MS Proyect, > > as in Planner, the cost of the Work Resources always it's rated with the > > hour's assignment, but, in some proyects You may to hire personal payed full > > time or part time, in this cases the costs are fixed. and the personal's > > budget too. > > > > I would like to find, as a option, to choose the kind of personal's payment, > > Fixed or rated by hours. > > Have a look at https://bugzilla.gnome.org/show_bug.cgi?id=138936 > > -- > Alexandre Franke > > > ------------------------------ > > _______________________________________________ > Planner-list mailing list > Planner-list gnome org > http://mail.gnome.org/mailman/listinfo/planner-list > > > End of Planner-list Digest, Vol 43, Issue 3 > ******************************************* Explore the seven wonders of the world Learn more! |