Was wondering why planner does not total the % complete of the parent
task as it does for the days?
Example:
Parent task |
|
83% |
25/08/08 |
28/11/09 |
|
child task – 1 |
100% |
|
|
|
child task – 2 |
100% |
|
|
|
child task – 3 |
100% |
|
|
|
child task – 4 |
75% |
|
|
|
child task – 5 |
100% |
|
|
|
child task – 6 |
100% |
|
|
|
child task – 7 |
5% |
|
|
Sergio
The parent is the average of all child tasks, 580 / 7.
|