I've looked at the planner file you sent me, but I've been unable to reproduce the problem. A few more questions: - Does the problem occur with all tasks? I see some of the tasks in the file already have a completion > 75% - Does the problem occur with newly created files? - Do none of the ways of changing completion work: * dragging completion in the gantt chart? * using the "Edit task properties" dialog? * enabling the "% Complete" column next to the gantt chart and editing there? Regards, Maurice. -- Maurice van der Pot Gentoo Linux Developer griffon26 gentoo org http://www.gentoo.org Gnome Planner Developer griffon26 kfk4ever com http://live.gnome.org/Planner
Attachment:
pgpKIwMY9GL41.pgp
Description: PGP signature