Re: [Planner] Tasks assigned to same resource scheduled concurrently?
- From: Josep Monés i Teixidor <jmones puntbarra com>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Tasks assigned to same resource scheduled concurrently?
- Date: Thu, 03 Mar 2005 15:35:25 +0100
El dj 03 de 03 del 2005 a les 15:01 +0100, en/na Josep Monés i Teixidor
va escriure:
> Ah Ok! I knew I could do it this way but I expected the software to do
> that automatically, because tasks aren't conceptually sequential, it's
> just a resource problem. If I assign, for instance, task2 to another
> resource, I have also to remember unlinking it (and possibly unlinking
> and relinking many tasks which depended on task2).
Hi again!
Now I found that this bug is exactly what is happening to me:
http://bugzilla.gnome.org/show_bug.cgi?id=167521
The proposed solution by Richard looks good for what I need at this
moment.
I'll workaoround it by making them depend on each other, as Massimo
suggested.
Thanks for your help!
Josep
[