Re: [Planner] Planner and 5 year projects ... back again



On sön, 2004-08-08 at 16:11 +0200, jan polcher wrote:
> Hello,
> 
> Now I have upgraded to planner version 0.12 and compiled myself. Thus I
> can go dig into the code to correct problems !
> 
> I have redone tests with this version and there is still a big issue
> with the lag of tasks.
> 
> Take an initial task and then add a second one. The second task can not
> have a lag larger than a week it seems. Does anyone know why there is
> this limit and where it can be changed ?

Hm, I just tried adding a predecessor with 10000 hours lag, and it
worked fine. Exactly how did you do?

/Richard

-- 
Imendio HB, http://www.imendio.com/