On Tue, 2006-06-20 at 07:37 +0200, Matteo Nastasi wrote:
> On Mon, Jun 19, 2006 at 07:49:50PM -0400, Kurt Maute wrote:
> > On Mon, 2006-06-19 at 10:07 +0200, Matteo Nastasi wrote:
> > > One step behind:
> > > 1) to develope the previously described features in an acceptable time,
> > > at least for the first devel iteration, we must inactivate all kinds
> > > of task's dependencies that imply retroactions (Kurt, don't hates
> > > me ;), because the interaction between retroactions and
> > > full_priority_scheduling enhances algorithms complexity very much.
> >
> > Could you clarify what you mean by retroactions? You mean maybe tasks
> > that calculate start date from the end date like FF & SF?
> Yes, the worst example is a snake chain of tasks like FS, FF, FS, FF ...
> with overlapping resources ;); leveling this configuration isn't
> simple.
Perhaps you could just make the leveling ignore tasks with those types
of dependencies for now?
--
Kurt Maute <kurt maute us>
[