Re: [Planner Dev] Reporting Actual Effort in the Tasks Page
- From: Cameron Shorter <shorterc2 optusnet com au>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: Re: [Planner Dev] Reporting Actual Effort in the Tasks Page
- Date: Sun, 15 May 2005 09:48:20 +1000
I'm considering writing XSL to extract BCWS and BCWP from the MrProject
format.
I'm guessing that if I write this properly, then it could slot quite
easilly into the HTML export function.
1. If I write this would developers be interested in it?
2. Is there anything I should consider (coding standards etc) before I
start?
Cameron Shorter wrote:
Hi,
I'm experimenting with using Planner to collect Earned Value
Management data and there are a couple of things that I think will be
easy to add to Planner to make help this.
Earned Value Management requires as inputs:
1. Budgeted Cost for Work Scheduled (BCWS)
This is basically a sum of the cumulative number of resources*labour
rate calculated on a day by day (or month by month) basis. It is
quite similar to a resource utilisation table.
2. Budgeted Cost of Work Performed (BCWP)
Without history, this can only be calculated for the current time in
the project. It involves working out how much work has been completed
and calculating a value for it.
3. Actual Cost of Work Performed (ACWP)
This data is usually collected from timesheets, not planner.
--
I'd suggest that 1 and 2 would be quite easy to produce. Has anyone
extracted this information before?
--
Cameron Shorter
http://cameron.shorter.net
[