On Wed, 2005-05-04 at 19:10 -0400, Frederic wrote:
> Hello,
>
> I have another question concerning the ressources usage. I think
> there is a bug with the computation. Indeed, I think if you have a task
> and subtask, automatically, you're at more than 100%. Do you experience
> the same problem or am I doing something wrong ? I use the 0.13 version.
Looks like a bug. I get the same result. If I create a summary task
with one subtask and assign the same resource to both at 100%, then the
resource appears as overallocated. I think we need to either disallow
the assignment of a resource to a summary task, or simply disable
resource usage calculations on summary tasks.
A workaround for now is to simply not assign a resource to a summary
task.
--
Kurt Maute <kurt maute us>
[