[Setup-tool-hackers] Status report. 27 January
- From: Chema Celorio <chema ximian com>
- To: miguel ximian com
- Cc: setup-tool-hackers ximian com
- Subject: [Setup-tool-hackers] Status report. 27 January
- Date: 27 Jan 2001 21:34:19 -0600
- Talked with all the team to get the status of the project.
Worked on a time schedule for the next preview release,laying
out the tasks that each team member is responsible for.
- Worked with pupi redesigning the structure of the backends so that
we can easily support more distros.
- Worked with ANA with the gui of the time-tool, the Internet Conection
druid and a group meeting where we discused the gui for time travel.
- Started working on the test suite infrastucture for XST
- Played with methathemes to get an general idea on where this project
is
I was not aware how time consuming managing a team can be.
I got very little hacking done because of managing stuff
like talking to the other guys about stuff they need to do.
It's not only a matter of letting them know what they need
to do, but it is important to discuss with them the technical
details about the task.
I also be I lost time with Traveling (monday), setting
up my computer (Tuesday) and during the week talking
to the markenting guys and stuff like that.
regards,
Chema
_______________________________________________
Setup-tool-hackers maillist - Setup-tool-hackers@helixcode.com
http://lists.helixcode.com/mailman/listinfo/setup-tool-hackers
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]