Re: Planner-list singletasking ressources
- From: Alexandre Franke <afranke gnome org>
- To: Nicolas Fueyo <nicolasfueyo hotmail com>
- Cc: "planner-list gnome org" <planner-list gnome org>
- Subject: Re: Planner-list singletasking ressources
- Date: Thu, 13 Jul 2017 11:02:20 +0200
On Wed, Jul 12, 2017 at 2:41 PM, Nicolas Fueyo <nicolasfueyo hotmail com> wrote:
Hello,
Hi,
Your mail was sent to moderation queue and I had to approve it because
you are not subscribed to the list. Consider subscribing to make sure
you get replies to your questions.
1° multitasking :
I use 1 ressource (me) and the software makes it like I can multitask
without limit. How can I set it so that 1 ressource is only used in one
task at a time ?
That’s called resource leveling and we don’t support it (yet). The
feature request is tracked at
https://bugzilla.gnome.org/show_bug.cgi?id=132917
2° total cost :
I defined a cost for the ressource. I think it is hour rate, but can't
find the total cost for the project.
This is tracked at https://bugzilla.gnome.org/show_bug.cgi?id=150532
--
Alexandre Franke
GNOME Hacker & Foundation Director
[