Hi,
On Wed, Oct 26, 2011 at 9:47 PM, Hartson, Brian
<brian hartson verizon com> wrote:
> I have several resources for a project with each having different days of
> availability. Is there a way to tie a different calendar to each resource?
Project → Manage calendars
to create as many calendars as you wish.
Right click on a resource in Resources view → Edit resource → Calendar tab
to assign a calendar to a given resource.
--