Hello, I'm new to Planner and am struggling to assign a fixed cost to a task. Currently, when I change the duration or the work length, the cost changes. The 'material' resource cost that I've assigned seems to scale with the number of days. I'm also struggling to find any on-line help - can you point me at any forums? (or is it fora?) Thanks in advance, Jolyon
|