Re: Planner-list Feature request: end by date



On Tue, May 4, 2010 at 5:01 AM, knubee <knubee gmail com> wrote:
>> It would be very useful to be able to specify that a task must END by
>> a specific date.

> i see now that i should submit feature requests via bugzilla for the project.

It's okay (and I'd even say it's appreciated) to discuss possible
improvements on the lists before filing a bug request.

> however, it would help tremendously to be able to specify an fixed end-date for
> a task. is there currently a workaround for this?

You can already do this.

Create a task and a milestone. Set date for milestone. Drag an arrow
from milestone to task. Edit task and go to Predecessors tab, set type
as SF (Start to Finish) which means that task must be finished when
milestone starts.

-- 
Alexandre Franke