Re: Planner-list Newbie question on task list



Hi Bill,

On Sat, Feb 20, 2010 at 12:41 AM, Bill Oliver <vendor billoblog com> wrote:
> I am using Planner for a multi-year project and notice that the Task
> disply provides "Start" and "Finish" columns.  When I choose those, I
> get the month and day, but not the year, e.g. "Jul 16" but not "Jul 16
> 2011."  The Gantt chart looks good.
>
> I can't find an option to change the appearance of the columns.  Is
> there a way to have it display the year as well as the month and day?

We don't support changing this at the moment. There's a feature
request for that at https://bugzilla.gnome.org/show_bug.cgi?id=136940
which you can add yourself to in the CC field to be kept up to date
regarding the issue.

-- 
Alexandre Franke


[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]