Re: Planner-list Base lining a task



On Mon, 2009-03-02 at 20:37 -0800, amitst wrote:
> I didn't find any feature in the Planner to base line the task so that if I
> have to again plan the task due to delays etc. the original plan is lost.
> 
> Can we have this feature in the Planner or is there any workaround to be
> used for this?

This feature has been discussed before, but hasn't yet been implemented.
http://bugzilla.gnome.org/show_bug.cgi?id=140676

I guess the only workaround for now is to save your baselined project
plan and copy it to a new one before making any updates/revisions.

-- 
Kurt Maute <kurt maute us>