Re: Planner-list One Afternoon Task



Hi,

One other way to do that is to modify your calendar for that day.

Create a new calendar based on the default one.
Change the working hours for that particular day.
Affect that calendar to the resource.

Max


Le jeudi 05 février 2009 à 13:00 -0800, Helder Mendes a écrit :
> Hi,
> 
> I beleive that to add lag time, I need to have a predecessor. I just want my task to start at 13:00H and last for 4hrs...
> 
> Thanks
> 
> --- On Thu, 2/5/09, Don Bish0p <dbishop bish0p org> wrote:
> 
> > From: Don Bish0p <dbishop bish0p org>
> > Subject: Re: Planner-list One Afternoon Task
> > To: heldermendes yahoo com
> > Date: Thursday, February 5, 2009, 4:12 PM
> > Just a thought -- can you add 4hrs lag time?
> > 
> > On Thu, 2009-02-05 at 04:22 -0800, Helder Mendes wrote:
> > 
> > > Hi There,
> > > 
> > > I'm having trouble, defining a few hours task,
> > say, 4hs during the afternoon. How can it be done?
> > > 
> > > If I define a 4h in the work time, it always starts in
> > the morning!
> > > 
> > > 
> > > Thanks in advance,
> > > HM
> > > 
> > > 
> > > 
> > >       
> > > _______________________________________________
> > > Planner-list mailing list
> > > Planner-list gnome org
> > > http://mail.gnome.org/mailman/listinfo/planner-list
> > > 
> > >
> 
> 
>       
> _______________________________________________
> Planner-list mailing list
> Planner-list gnome org
> http://mail.gnome.org/mailman/listinfo/planner-list