Re: Planner-list One Afternoon Task
- From: Massimiliano Franco <max-lists ycom ch>
- To: planner-list gnome org
- Subject: Re: Planner-list One Afternoon Task
- Date: Fri, 06 Feb 2009 08:14:33 +0100
Hi,
One other way to do that is to modify your calendar for that day.
Create a new calendar based on the default one.
Change the working hours for that particular day.
Affect that calendar to the resource.
Max
Le jeudi 05 février 2009 à 13:00 -0800, Helder Mendes a écrit :
> Hi,
>
> I beleive that to add lag time, I need to have a predecessor. I just want my task to start at 13:00H and last for 4hrs...
>
> Thanks
>
> --- On Thu, 2/5/09, Don Bish0p <dbishop bish0p org> wrote:
>
> > From: Don Bish0p <dbishop bish0p org>
> > Subject: Re: Planner-list One Afternoon Task
> > To: heldermendes yahoo com
> > Date: Thursday, February 5, 2009, 4:12 PM
> > Just a thought -- can you add 4hrs lag time?
> >
> > On Thu, 2009-02-05 at 04:22 -0800, Helder Mendes wrote:
> >
> > > Hi There,
> > >
> > > I'm having trouble, defining a few hours task,
> > say, 4hs during the afternoon. How can it be done?
> > >
> > > If I define a 4h in the work time, it always starts in
> > the morning!
> > >
> > >
> > > Thanks in advance,
> > > HM
> > >
> > >
> > >
> > >
> > > _______________________________________________
> > > Planner-list mailing list
> > > Planner-list gnome org
> > > http://mail.gnome.org/mailman/listinfo/planner-list
> > >
> > >
>
>
>
> _______________________________________________
> Planner-list mailing list
> Planner-list gnome org
> http://mail.gnome.org/mailman/listinfo/planner-list
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]