Hi,
I'm planning a project with the great planner tool. But I'm confused by the
way, resources are handled.
I defined resources, especially a team named OS6 (type work) and tasks. The
tasks named Server and Authentication require the resource OS6 by 100% each.
I mean, the two tasks should be one after the other, because the team can do
only one job at a time: 1st Server (prio 8), then Athentication (prio 4).
planner puts the two tasks into the same time slice an produces a resource
usage of 200%.
How can I get it working?
(planner 0.14.2 on openSuse 10.3)
BTW: Is there an online manual? I didn't find one with the distribution nor at
gnome.org.
Thanx, Regards
Joachim Fehn
--
Joachim Fehn Senior Expert Developer -- IP SW OS 6
Fujitsu Siemens Computers GmbH www.fujitsu-siemens.de
Otto-Hahn-Ring 6 www.fujitsu-siemens.de/imprint.html
D-81739 Muenchen Joachim Fehn fujitsu-siemens com
[Date Prev][
Date Next] [Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]