On Fri, Oct 10, 2008 at 06:53:09PM +0100, Rich Coombs wrote: > I would like to know how I include a holiday period in my gantt chart. I.e. > a week or so where no progress will be made on the project as it is the > Christmas holiday or something like that. You do that by marking these days as non-working in the project calendar. It's under Project -> Manage Calendars. Set the day type to non-working and click Apply. Regards, Maurice. -- Maurice van der Pot Gentoo Linux Developer griffon26 gentoo org http://www.gentoo.org Gnome Planner Developer griffon26 kfk4ever com http://live.gnome.org/Planner