On Wed, Jul 09, 2008 at 12:44:18PM +0200, Philippe Dhont  (Sea-ro) wrote:
> - I have a task and subtasks.
> How can I change the date of the task ?
> I cannot change it, is it because of all the subtasks ?

You should be able to change the start date by either:
- adding a predecessor task that forces it to start later, or
- change the schedule mode from "as soon as possible" to "no earlier
  than" or "on fixed date" in the task properties dialog.

If it still doesn't work, please submit a bug report with your planner
version, instructions how to reproduce the problem and, if it does not
always happen, a planner file that exhibits the problem.

> - is there a possibility to SEE the days in the html export or the
> printout?
> Like Mon, Tue, WED, ...
> That would be nice.

Not at the moment, but it is planned. See the following bugs & message:
http://bugzilla.gnome.org/show_bug.cgi?id=129141
http://bugzilla.gnome.org/show_bug.cgi?id=151481
http://mail.gnome.org/archives/planner-list/2007-October/msg00001.html

Regards,
Maurice.

-- 
Maurice van der Pot

Gentoo Linux Developer   griffon26 gentoo org    http://www.gentoo.org
Gnome Planner Developer  griffon26 kfk4ever com  http://live.gnome.org/Planner

Attachment: pgpwKFcs2tKeS.pgp
Description: PGP signature



[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]